KEN TOWER – RAJASINGHE ROAD
Ken Tower Rajasinghe Road, Colombo 06 apartments sit in close proximity to Marine Drive as well as Galle Road and other important locations including schools, hospitals, banks, supermarkets and entertainment venues.
Apartments offer stunning views of the turquoise waters of the majestic Indian Ocean while the cool breeze will help rejuvenate your senses. Modern amenities and thoughtful facilities make this an ideal choice if you are looking for a luxury apartment in Colombo.
Key Features
Features
Designed to ensure
– Privacy
– Easy parking & Accessibility
– Pleasing Interiors
– Security
Amenities
– ceiling fans in living,Dining and all rooms
– Air conditioning in One bedroom
– Intercom system
Finishes
WALL – Emulsion paint in pleasing shades
FLOOR – Imported tiles in living and dining rooms, non slippery tiles in bathrooms, Heavy duty ceramic tiles in the common area
WINDOW – Rust proof powder coated aluminum windows (Anti Corrosive)
DOORS – High quality solid timber doors and Yale lock set at entrance Teak Varnished class 1 plywood doors matte finished with wood sheen paint, else ware PVC doors for bathrooms
PANTRY – pantry cupboards (bottom unit) with granite top & stainless steel sink
BATHROOM – Hot water geyser in Master bathroom
Common Facilities
ELEVATOR – One number high speed Elevator
STANDBY GENERATOR -Backup power supply for common area
FIRE PROTECTION SYSTEM – Fire extinguishers, wet rise system, house reels and exit signs.
GARBAGE COLLECTION – Storage area in ground floor with trolleys for collection and transfer to C.M.C Truck
OTHER
– Reception, Visitors lobby, Maintenance office
– 24 hours security
Special Integrates
– Swimming pool
– Gymnasium
Floor Plan
Location
Availability
Floor | Unit A 1240 Sqft | Unit B 870 Sqft | Unit C 1170 Sqft | Unit D 500 Sqft |
---|---|---|---|---|
1st | SOLD | SOLD | SOLD | SOLD |
2nd | SOLD | SOLD | SOLD | SOLD |
3rd | SOLD | SOLD | SOLD | SOLD |
4th | SOLD | SOLD | SOLD | SOLD |
5th | SOLD | SOLD | SOLD | SOLD |
6th | SOLD | SOLD | SOLD | SOLD |
7th | SOLD | SOLD | SOLD | SOLD |
8th | SOLD | SOLD | SOLD | SOLD |
Current Status
completion of Exterior wall paint works – 27th March 2019
completion of Bathroom fitting works – 03th March 2019
Vehicle lift fixing completed – 21th February 2019
wall lights and seiling lights &seiling fan installation completed – 08th February 2019
ongoing common area louver window & fixed glass window work – 29th January 2019
Common area & staircase tilling work completed – 25th January 2019
first floor Tie beam painting – 19th January 2019
ongoing internal wall painting – 03th January 2019
ongoing External wall painting – 28th December 2018
ongoing common area tiling work – 23th December 2018
Electrical work – 10th December 2018
Ongoing kitchen pantry cupboards installation – 05th December 2018
main door and bedroom door work completed – 22nd November 2018
Ongoing lift installation work& tiling work – 09th November 2018
Ongoing Main door spray work – 15th October 2018
Ongoing tiling & Main door fixing – 08th October 2018
Ongoing Tiling & carpentry works – 13th September 2018
Roof top slab concreting – 05th March 2018
09th slab Concreting – 14th February 2018
08th slab Concreting – 25th January 2018
07th slab reinforcement – 4th January 2018
06th slab concreting – 25th December 2017
5th slab concreting – 07th December 2017
4th slab concreting – 10th November 2017
3rd floor slab concreting – 11th October 2017
2nd slab column erection completed – 18th September 2017
2nd slab concreting – 31st August 2017
ongoing Second slab reinforcement – 28th August 2017
First Slab wall column concreting – 13th July 2017
First floor slab concreting – 23rd June 2017
Ongoing First slab form work – 06th June 2017
Ground floor column concrete completed and sand filling – 28th April 2017
Soil filling and column reinforcement – 24th March 2017
Basement raft concrete – 08th March 2017
Foundation Reinforcement – 04th January 2017
Soil investigation – 16th May 2016